VIENIDMY Sign in Start practicing

Home › Sample questions › Production Management Operations Grade 3 生産管理オペレーション (BC検定)

BC Kentei Production Management Operations Grade 3 practice test with answers – free sample questions

ビジネス・キャリア検定 生産管理オペレーション3級

10 sample questions in the real exam format, with furigana, English translation, answers and explanations. Tap "Show answer" under each question. For the full question bank and realistic mock exams, open the free app.

Question 1

Which of the following statements is MOST INAPPROPRIATE regarding production systems and the objectives of production management (QCD)?

  1. A.
    In shop-floor production management, reducing manufacturing Cost (C) takes top priority, so design Quality (Q) or specified Delivery dates (D) may be relaxed at the shop floor's discretion to meet cost targets.
  2. B.
    The three basic objectives of production management, QCD, are to achieve Quality, Cost, and Delivery as well as quantity in accordance with the customer's required standards.
  3. C.
    A trade-off relationship may arise among QCD elements; for example, trying to improve Quality (Q) often requires extra inspection or expensive materials, which tends to increase Cost (C).
  4. D.
    A production system is a mechanism that takes in management resources such as Man, Machine, and Material, and outputs products through a transformation process.
Show answer

Correct answer: A

The purpose of production management is to maintain an optimal balance among Quality (Q), Cost (C), and Delivery (D) to satisfy customer requirements; the shop floor must never arbitrarily lower design quality standards or delay delivery dates merely to reduce manufacturing cost. The statements regarding the 3M input-to-output transformation process, the meaning of QCD, and the trade-off relationships among Q, C, and D are all correct. (Textbook: Basics of Work Management - Production Systems)

WordMeaning
production system (seisan shisutemu)
management resources (3M: Man, Machine, Material)
trade-off relationship (niritsu haihan)

Question 2

When the net time per unit for an assembly operation was measured, the sum of the elemental operations was 120 seconds. Based on the allowance rate data in the table below, which of the following is the MOST APPROPRIATE value for the standard time per unit calculated using the external ratio method (outside multiplication method)? Breakdown of allowance rates: ・Personal allowance rate: 3% ・Fatigue allowance rate: 5% ・Workshop allowance rate: 7%

  1. A.
    132 seconds
  2. B.
    138 seconds
  3. C.
    141 seconds
  4. D.
    145 seconds
Show answer

Correct answer: B

Total allowance rate = 3% + 5% + 7% = 15% (0.15). Under the external ratio method (外掛け法), the standard time per unit is calculated as: Standard time = Net time × (1 + Total allowance rate) = 120 × (1 + 0.15) = 120 × 1.15 = 138 seconds. The value 132 seconds omits the 5% fatigue allowance rate; 141 seconds wrongly divides by (1 − 0.15) using the internal ratio method (120 ÷ 0.85 ≈ 141.2 seconds); 145 seconds miscalculates the allowance rate. (Textbook: Basics of Work Management - Setting Standard Time)

💡 Standard time formula under the external ratio method: Standard time = Net time × (1 + Total allowance rate). Here, 120 seconds × (1 + 0.03 + 0.05 + 0.07) = 138 seconds.

WordMeaning
standard time (hyōjun jikan)
net time and allowance time
external ratio method (sotogake-hō)

Question 3

Which of the following statements is MOST INAPPROPRIATE regarding the objectives and functions of process management?

  1. A.
    The main objectives of process management include ensuring delivery dates, shortening manufacturing lead time, reducing work-in-process inventory, and improving the utilization of equipment and workers.
  2. B.
    Constantly holding a large amount of work-in-process inventory between processes to prevent stockouts and delivery delays directly shortens manufacturing lead time and reduces working capital.
  3. C.
    If large-lot advance production is carried out with an excessive focus on raising the utilization rate of equipment and workers, work-in-process inventory between processes tends to increase.
  4. D.
    Process management consists of two functions: production planning, which sets targets and procedures for production activities, and production control, which monitors and adjusts progress to match the plan.
Show answer

Correct answer: B

Holding a large amount of work-in-process (WIP / 仕掛品) inventory between processes increases waiting and retention time, which lengthens manufacturing lead time, ties up working capital, and consumes factory floor space. A core objective of process management is to reduce work-in-process inventory while still meeting delivery dates. All other statements are correct. (Textbook: Basics of Process Management - Concept of Process Management)

WordMeaning
process management (kōtei kanri)
manufacturing lead time (seizō rīdotaimu)
work-in-process inventory (shikakarihin)

Question 4

Which of the following statements is MOST INAPPROPRIATE regarding master scheduling (long-term), medium-term scheduling, and short-term scheduling in production scheduling?

  1. A.
    Master scheduling (large schedule) covers a period of about six months to a year, establishing monthly production frameworks and plans for long-lead-time items based on sales plans and order forecasts.
  2. B.
    Medium-term scheduling covers a period of about one to several months, determining production quantities and start/completion dates by product to balance load and capacity across processes.
  3. C.
    Short-term scheduling (small schedule) covers a short period of one day to one week, assigning specific work sequences and schedules to individual machines and workers in the workshop.
  4. D.
    Short-term scheduling is a long-range strategic plan used by top management to decide on building new factories or making capital investments, and is never changed by daily shop-floor progress.
Show answer

Correct answer: D

Short-term scheduling (小日程計画) is an operational schedule covering one day to one week that assigns daily work sequences to individual machines and workers on the shop floor, and it is adjusted flexibly in response to daily production progress. Decisions on new factories or capital investment belong to long-range corporate planning by top management. (Textbook: Basics of Process Management - Production Scheduling)

WordMeaning
master / long-term schedule (dainittei keikaku)
medium-term schedule (chūnittei keikaku)
short-term / operational schedule (shōnittei keikaku)

Question 5

Which of the following statements is MOST INAPPROPRIATE regarding equipment management characteristics (economic efficiency, reliability, and maintainability)?

  1. A.
    Equipment reliability is the property of performing its intended function without failure for a specified period under stated conditions; a smaller Mean Time Between Failures (MTBF) indicates higher reliability.
  2. B.
    Equipment maintainability is the property representing how easily inspection and repairs can be performed when a failure occurs; a smaller Mean Time To Repair (MTTR) indicates better maintainability.
  3. C.
    When evaluating the economic efficiency of equipment, judgment must be based on the total Life Cycle Cost (LCC), including not only initial acquisition cost but also operating and maintenance costs.
  4. D.
    The proportion of time that equipment is in an operable state whenever needed (availability) is calculated using the formula 'MTBF ÷ (MTBF + MTTR)'.
Show answer

Correct answer: A

Mean Time Between Failures (MTBF) represents the average operating time between one failure and the next; therefore, a LARGER MTBF value means fewer failures and higher equipment reliability. Conversely, a smaller Mean Time To Repair (MTTR) means faster repairs and better maintainability. (Textbook: Basics of Equipment Management - Concept of Equipment Management)

💡 Equipment reliability and maintainability: a LARGER MTBF (Mean Time Between Failures) means higher reliability; a SMALLER MTTR (Mean Time To Repair) means better maintainability. Availability = MTBF ÷ (MTBF + MTTR).

WordMeaning
Mean Time Between Failures (MTBF)
Mean Time To Repair (MTTR)
availability (kadōritsu)

Question 6

As shown in the illustration, cardboard boxes containing products are neatly stacked on a wooden pallet in a factory storage area. Which of the following combinations of the 'Material Handling Liveliness Index' for this state and its reason is MOST APPROPRIATE?

As shown in the illustration, cardboard boxes containing products are neatly stacked on a
  1. A.
    The Material Handling Liveliness Index is '0', because it is the same as items scattered loose on the floor and requires all 4 handling actions: piling up, placing onto a support, lifting up, and pulling away.
  2. B.
    The Material Handling Liveliness Index is '1', because being packed in boxes eliminates only the 'piling up' action while still requiring the remaining 3 handling actions.
  3. C.
    The Material Handling Liveliness Index is '2', because being unitized on a pallet eliminates the 2 actions of 'piling up' and 'placing onto a support', requiring only the 2 actions of 'lifting up and pulling away'.
  4. D.
    The Material Handling Liveliness Index is '3', because it is equivalent to being placed on a wheeled handcart and can be moved with just the 1 action of 'pulling away'.
Show answer

Correct answer: C

In the illustration, cardboard boxes are stacked neatly on a wooden pallet resting on the floor (パレット置き). Under the Material Handling Liveliness Index (運搬活性示数 = 4 − number of manual actions needed among piling up, placing onto a support, lifting up, and pulling away): loose on the floor is 0 (needs all 4 actions); boxed or bundled on the floor is 1; stacked on a pallet (as shown) eliminates 'piling up' and 'placing onto a support', leaving only 'lifting up' and 'pulling away' (4 − 2 = 2); on a wheeled cart is 3; moving on a conveyor is 4. (Textbook: Basics of Material Handling and Logistics - Liveliness Index)

💡 Material Handling Liveliness Index (0 to 4): Loose on floor = 0; Boxed on floor = 1; Stacked on a wooden pallet = 2 (only lifting up and pulling away needed); Wheeled handcart = 3; Moving conveyor = 4.

WordMeaning
Material Handling Liveliness Index (unpan kassei shisū)
palletized storage (paretto-oki)
Material Handling (MH)

Question 7

Which of the following statements is MOST INAPPROPRIATE regarding 'quality of design vs. quality of conformance' and 'true quality characteristics vs. substitute quality characteristics' in quality control?

  1. A.
    Quality of design (targeted quality) is the quality level planned and designed as a target by the company based on market research and customer needs.
  2. B.
    Quality of conformance (manufactured quality) represents how closely the actually manufactured product conforms to the targeted design drawings and specifications.
  3. C.
    True quality characteristics are the quality properties that consumers genuinely seek when using a product, such as 'a ballpoint pen that writes smoothly' or 'a long-lasting battery'.
  4. D.
    Substitute quality characteristics are subjective properties that cannot be quantified with factory measuring instruments and are evaluated purely by intuition through consumer questionnaires.
Show answer

Correct answer: D

Because 'true quality characteristics' (真の特性 — customer desires like 'writes smoothly' or 'durable') are often qualitative and difficult to measure directly on a factory line, manufacturers translate them into quantifiable physical or chemical parameters measurable with factory instruments (such as ink viscosity, ball diameter, tensile strength, or mAh capacity), which are called 'substitute quality characteristics' (代用特性). Claiming that substitute quality characteristics cannot be quantified with factory measuring instruments is incorrect. (Textbook: Quality Control - Concept of Quality Control)

💡 Quality pairs: Quality of design = targeted quality; Quality of conformance = manufactured quality. True quality characteristics = what consumers seek; Substitute quality characteristics = quantifiable factory metrics.

WordMeaning
quality of design and quality of conformance
true quality characteristic (shin no tokusei)
substitute quality characteristic (daiyō tokusei)

Question 8

Given the monthly cost data for a factory in the table below, which of the following combinations of 'Manufacturing Cost' and 'Total Cost' for the month is MOST APPROPRIATE? Monthly cost data: ・Direct material cost: 4,000,000 yen ・Direct labor cost: 2,500,000 yen ・Direct expenses (subcontract processing cost): 500,000 yen ・Manufacturing overhead (indirect cost): 1,800,000 yen ・Selling, general and administrative (SG&A) expenses: 1,200,000 yen

  1. A.
    Manufacturing Cost: 8,800,000 yen / Total Cost: 10,000,000 yen
  2. B.
    Manufacturing Cost: 7,000,000 yen / Total Cost: 8,800,000 yen
  3. C.
    Manufacturing Cost: 8,300,000 yen / Total Cost: 9,500,000 yen
  4. D.
    Manufacturing Cost: 10,000,000 yen / Total Cost: 11,200,000 yen
Show answer

Correct answer: A

Direct manufacturing cost = Direct material cost (4,000,000) + Direct labor cost (2,500,000) + Direct expenses (500,000) = 7,000,000 yen. Manufacturing Cost (製造原価) = Direct manufacturing cost (7,000,000) + Manufacturing overhead (1,800,000) = 8,800,000 yen. Total Cost (総原価) = Manufacturing Cost (8,800,000) + Selling, general and administrative expenses (1,200,000) = 10,000,000 yen. The combination of 7,000,000 and 8,800,000 yen confuses direct cost with manufacturing cost; 8,300,000 and 9,500,000 yen omits direct expenses of 500,000 yen. (Textbook: Cost Management - Cost Structure)

💡 Cost structure formulas: Direct cost = Direct material + Direct labor + Direct expenses. Manufacturing Cost = Direct cost + Manufacturing overhead. Total Cost = Manufacturing Cost + SG&A expenses.

WordMeaning
direct manufacturing cost and manufacturing overhead
manufacturing cost and total cost
selling, general and administrative (SG&A) expenses

Question 9

Which of the following statements is MOST INAPPROPRIATE regarding 'delivery delay' and 'early delivery (delivering much earlier than the specified delivery date)' in delivery management?

  1. A.
    Early delivery is always welcomed by customers as a good service, so as soon as products are completed, they should be shipped immediately without customer consent regardless of how many days early it is.
  2. B.
    Early delivery—shipping products much earlier than the specified delivery date—must be avoided because it crowds the customer's storage space and increases inventory management costs.
  3. C.
    In one's own factory, unnecessarily advancing the production of orders that still have ample time before their delivery date can delay the production of other orders that are truly urgent.
  4. D.
    When a delivery delay occurs, it can cause damage such as stopping the customer's production line, leading to a loss of corporate credibility or termination of business.
Show answer

Correct answer: A

In delivery management (納期管理), the fundamental rule is delivering the exact required quantity on the exact specified delivery date (Just-In-Time). Shipping products early without the customer's consent crowds the customer's warehouse space, increases inventory holding costs, and disrupts receiving schedules, while unnecessary advance production in the factory delays urgent orders. (Textbook: Delivery Management - Concept of Delivery Management)

💡 In delivery management, both delivery delay and unauthorized early delivery must be avoided: early delivery crowds the customer's storage space, increases inventory costs, and delays urgent orders.

WordMeaning
delivery management (nōki kanri)
adverse effects of early delivery (sōki nōnyū no heigai)
advance production ahead of schedule (maedaoshi seisan)

Question 10

Which of the following statements is MOST INAPPROPRIATE regarding the occupational safety and health management system at a workplace under the Industrial Safety and Health Act?

  1. A.
    A Safety Officer manages technical matters related to safety, such as emergency measures and preventive measures when hazards exist in buildings, equipment, work areas, or work methods.
  2. B.
    A Health Officer must patrol the workplace at least once every week to inspect equipment and sanitary conditions in order to prevent health impairments among workers.
  3. C.
    An Industrial Physician is a medical doctor who manages workers' health, but only needs to conduct health consultations in the clinic room and has no obligation to patrol the factory work areas.
  4. D.
    In the manufacturing industry, at workplaces regularly employing 50 or more workers, the employer must appoint both a Health Officer and an Industrial Physician.
Show answer

Correct answer: C

Under the Industrial Safety and Health Act (労働安全衛生法), an Industrial Physician (産業医) is legally required to patrol the factory workplace in person at least once every month (or at least once every two months if the employer consents and weekly patrol results from the Health Officer are reported monthly) to inspect working conditions and take immediate health protection measures when needed. A Health Officer (衛生管理者) must patrol at least once a week. (Textbook: Safety and Health Management - Safety and Health Management System)

WordMeaning
Safety Officer (anzen kanrisha)
Health Officer (eisei kanrisha)
Industrial Physician (sangyōi)
Practice the full question bank and mock exams in the app

Lessons: Production Management Operations Grade 3 生産管理オペレーション (BC検定)

Zalo